Silos de Damen

Demolition and Paving

Click any date or image below to see more.

Backstory and original documents collected by MPDC. Full analysis as published in MAS Context.

Aug 19: 2nd Court Hearing
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Aug 19: 2nd Court Hearing

At MAT’s second hearing, the case was continued until October 8, with an agreement that they have until September 30 to apply for required permits…

Seguir leyendo
Aug 10: Electrical Work + Asphalt Closeup
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Aug 10: Electrical Work + Asphalt Closeup

Electrical contractor Gibson continues work near the construction trailers during increased vehicle activity on the site. Closeups of the asphalt show that it was not laid over the reservoir layer required for permeable pavement, as required by industry standards and previously claimed in court. The stack of wooden beams grows.

Seguir leyendo
Aug 6: Building Materials and More Equipment Arrive
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Aug 6: Building Materials and More Equipment Arrive

Deliveries continue at the Silos, including large beams, heavy equipment, and more trailers. Total trailer count is now 14, and workers are moving materials like drywall into the trailers.

Dirt is being moved on the unpaved portion of the site, and new fencing is up.

Seguir leyendo
July 30: First Court Hearing
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

July 30: First Court Hearing

The City of Chicago is suing MAT, which has 5 counts against it. None of MAT’s owners appeared at the hearing…

Seguir leyendo
July 2: New Pavement Extended, Gate Added
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

July 2: New Pavement Extended, Gate Added

Despite a city citation, MAT has added a new gate at the southeast corner of the lot, paved a path from that gate to the lot next door, and put up jersey barriers to protect that path. A trailer and multiple portajohns have also been brought in.

Seguir leyendo
June 18: Parking Lot Overview
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

June 18: Parking Lot Overview

City departments investigate the unsanctioned parking lot and issue citations. MAT owners suggest in the press that the pavement is permeable. MAT Asphalt, which did the paving and shares ownership with the Silos, does not manufacture or install permeable pavement.

The Lake Street Bridge takes shape on the dock.

Seguir leyendo
June 15-16: Parking Lot Constructed Overnight
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

June 15-16: Parking Lot Constructed Overnight

A parking lot covering approximately 1/3 of the 23 acres at Damen Silos was constructed overnight without permitting or other official oversight.

A neighbor departing for night shift around 7 PM saw heavy vehicles pull in as they passed by, and found the lot completed when they returned home in the morning.

Seguir leyendo
June 1, 2026: Machines Move Dirt Onsite
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

June 1, 2026: Machines Move Dirt Onsite

In a new wave of activity, machines move dirt on site at Damen Silos. Concrete blocks are piled near the Damen overpass, and piles of dirt are made nearby.

Meanwhile, floating docks are prepared for the construction of the Lake Street Bridge in the adjacent Santa Fe Slip, located on the east side of the Silos property. MAT is a subcontractor on the bridge contract, paid to provide a construction location.

Seguir leyendo
Dec 17: Only Bases of Structures Remain
Usuario invitado Usuario invitado

Dec 17: Only Bases of Structures Remain

All 12 silos and the tower of the river edge structure have been brought down to their bases. Only remnants of the structures are left standing as a sheet of ice freezes over the site.

Seguir leyendo
Nov 6: The Tower Comes Down Slowly, as Bricks are Packed Up
Usuario invitado Usuario invitado

Nov 6: The Tower Comes Down Slowly, as Bricks are Packed Up

Demolition of the tower continues in tandem with the remainder of the last silo. Work at this height moves more slowly, leaving behind a gaping hole.

Meanwhile, bricks from the building along the Santa Fe Slip are packaged for storage. As a condition of the federal demolition permit, the bricks must be saved and integrated into a future riverfront path.

Seguir leyendo
Oct 28: The First Bite From the Tower
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Oct 28: The First Bite From the Tower

A wrecker takes the first bite out of the 110-ft tall structure after Department of Buildings paused work for several days to develop a safety plan for this part of the operation. With the rest of the structure removed or degraded, there is no longer a wind break to reduce dust, and gusts pose a greater risk to the demolition crew.

Seguir leyendo
Oct 21: Last Silo Hangs On
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Oct 21: Last Silo Hangs On

The remainder of the last silo clings onto the tower as its contents are trucked out. Water sprayers attached to the equipment aren’t enough to prevent dust from scattering in the wind.

Seguir leyendo
Oct 14: River Barrier Replaced, Filled Silo Slows Work
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Oct 14: River Barrier Replaced, Filled Silo Slows Work

After a brief pause in work while the river barrier was replaced, demolition activity resumed. Workers opened the filled silo, spilling a large pile of material on the back side of the building. Multiple large sprayers were positioned to control the resulting dust.

Seguir leyendo
Oct 10: River Barrier Breaks Loose
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Oct 10: River Barrier Breaks Loose

The river barrier in front of the Silos is intended to block debris off the site from floating downstream. Around 11:30 this morning, the barrier itself broke loose and drifted off.

Seguir leyendo
Oct 3: Demo Team and CDPH Meet Onsite
Consejo de Desarrollo de McKinley Park Consejo de Desarrollo de McKinley Park

Oct 3: Demo Team and CDPH Meet Onsite

CDPH and the demolition team meet onsite, we assume for purposes of making a new dust plan. While no further demolition occurs today, crews continue to clean up near the silos.

Seguir leyendo